So What Club

Data centre economics: per MW, per rack and per GPU hour

Work out rent and return per megawatt for colocation, racks from a power budget, and profit per GPU hour for an AI cloud, and see why utilisation, price and chip life decide everything.

Lesson 2 of 3 · 12 min

The idea

Two businesses sit in one building. Colocation earns rent per kW for 10 to 15 years on a building that lasts decades, so it looks like property. A GPU cloud earns per GPU hour on chips that lose value in a few years, so it lives or dies on utilisation (the share of hours its chips are rented out), price and how fast the chips must be paid back.

Reference prices and costs (checked 30 September 2026)
Reference prices and costs (checked 30 September 2026)
ItemRangeSource
Build cost, all in, greenfield, US and Canada, excluding chipsAbout USD 8.9 million to 23.3 million per MW, up about 21 percent since late 2024Cushman & Wakefield 2026 cost guide, as reported
Colocation asking rent, Silicon ValleyAbout USD 180 to 275 per kW per monthCBRE, second half of 2025
Primary US market vacancyAbout 1.4 percent, a record lowCBRE, H1 2026
H100 GPU, on-demand, specialist GPU cloud list priceAbout USD 4 per GPU hourLambda price list, September 2026
H100 GPU, AWS on-demand price cut in June 2025Up to about 45 percentAWS, June 2025

So-what

Prices differ a lot by market, contract length and size: a 20 MW hyperscale lease pays far less per kW than a few racks, and long GPU contracts cost less per hour than on-demand. Treat these as reference points, not a price list.

Worked case

Return per MW for a colocation campus near Mumbai

Case

A developer plans a 20 MW colocation campus near Mumbai and reports in USD. It costs USD 10 million per MW of IT load to build, excluding the customers' servers. It expects to lease 90 percent of the capacity at an average rent of USD 150 per kW per month; customers pay for their own electricity on top. Operating costs that are not passed through (staff, maintenance, insurance, security) are USD 400,000 per MW of built capacity a year. What are yearly revenue and operating profit, the yield on cost, and the simple payback? (Figures are illustrative.)

The companies and figures in this case are made up for practice, unless a source is named.

Questions to ask

Situation

  • Who is the developer, and what is the plan?

    What the interviewer says

    The data centre arm of a Mumbai property group. It plans 20 MW of IT load on one plot in Navi Mumbai, built in two 10 MW phases.

History

  • Has the group built data centres before?

    What the interviewer says

    No. It has built office parks for 15 years and bought this land in 2024.

Objective

  • What does the board need to decide?

    What the interviewer says

    Whether to approve USD 200 million. It wants a yield on cost of at least 10 percent before depreciation.

Financials

  • What does it cost to build and run?

    What the interviewer says

    USD 10 million per MW of IT load, excluding customers' servers. Running costs that are not passed through are USD 400,000 per MW a year.

  • What will customers pay?

    What the interviewer says

    About USD 150 per kW of IT load per month, plus their own electricity, which is passed through at cost.

Market

  • How tight is the market?

    What the interviewer says

    For reference, CBRE reported US primary market vacancy of about 1.4 percent in the first half of 2026. The group's broker puts Mumbai rents at USD 120 to 170 per kW per month.

  • Is USD 10 million per MW a normal build cost?

    What the interviewer says

    Cushman and Wakefield's 2026 guide put US and Canada costs at about USD 8.9 million to 23.3 million per MW, up about 21 percent since late 2024.

Customers

  • Who wants the space?

    What the interviewer says

    Two cloud firms and a bank are in talks. One cloud firm will take 8 MW at USD 130 per kW per month if it signs before construction.

Competitors

  • Who else is building nearby?

    What the interviewer says

    Three large operators are building campuses in Navi Mumbai, adding several hundred MW over the next three years.

Operations

  • When will power be available?

    What the interviewer says

    The state utility has promised a 30 MW connection in 18 months, enough for 20 MW of IT load plus cooling. Transformers take about 12 months to arrive.

  • What cooling is planned?

    What the interviewer says

    A design PUE of 1.4, with an option to add liquid cooling for AI racks later. A rooftop solar plan is also being studied.

Constraints

  • How will it be funded?

    What the interviewer says

    Lenders will fund 60 percent if the group puts in 40 percent as equity.

Exhibits

Exhibit 1

Yield on cost by share of the campus leased, at USD 150 per kW per month (percent)(%)

Bar chart: Yield on cost by share of the campus leased, at USD 150 per kW per month (percent). 70 percent leased: 8.6 percent; 80 percent leased: 10.4 percent; 90 percent leased: 12.2 percent; 100 percent leased: 14 percent.

Illustrative figures. Build cost USD 200 million; running costs USD 8 million a year.

Exhibit 2

The campus with and without the anchor tenant (USD millions a year unless stated)
The campus with and without the anchor tenant (USD millions a year unless stated)
CaseRevenueOperating profitYield on cost (percent)
18 MW leased at USD 15032.424.412.2
8 MW at USD 130, 10 MW at USD 15030.4822.4811.24

Illustrative figures.

Solution

Show the solution

Structure

  • Return per MW = (rent from leased MW minus operating costs) / build cost
    • Revenue = MW x 1,000 kW x leased share x rent per kW x 12 months
    • Operating profit = revenue minus operating costs
    • Yield on cost = operating profit / build cost
    • Payback = build cost / operating profit, in years

Analysis

  1. 1. Build cost

    20 MW at USD 10 million each, in USD millions.

    Build cost (USD millions): 20 × 10 = 200

  2. 2. Yearly rent

    20,000 kW, 90 percent leased, at USD 150 a month for 12 months, in USD millions.

    Yearly revenue (USD millions): 20 × 1,000 × 0.9 × 150 × 12 ÷ 1,000,000 = 32.4

  3. 3. Operating costs

    USD 0.4 million per MW on all 20 MW built.

    Yearly operating costs (USD millions): 20 × 0.4 = 8

  4. 4. Operating profit

    Revenue minus operating costs, before depreciation, interest and tax.

    Yearly operating profit before depreciation (USD millions): 32.4 - 8 = 24.4

  5. 5. Yield on cost

    Operating profit divided by build cost.

    Yield on cost (percent): 24.4 ÷ 200 × 100 = 12.2

  6. 6. Simple payback

    Build cost divided by yearly operating profit.

    Simple payback (years): 200 ÷ 24.4 = 8.2

  7. 7. Leased share needed for a 10 percent yield

    The board wants USD 20 million of operating profit on USD 200 million, so revenue must cover that plus USD 8 million of costs. Full leasing would bring USD 36 million.

    Leased share needed (fraction): (200 × 0.1 + 8) ÷ (20 × 1,000 × 150 × 12 ÷ 1,000,000) = 0.7778

  8. 8. Revenue with the anchor tenant

    The anchor takes 8 MW at USD 130; another 10 MW lets at USD 150, so 90 percent is still leased.

    Yearly revenue with the anchor (USD millions): (8,000 × 130 + 10,000 × 150) × 12 ÷ 1,000,000 = 30.48

  9. 9. Yield on cost with the anchor

    Revenue minus USD 8 million of costs, over USD 200 million.

    Yield on cost with the anchor (percent): (30.48 - 8) ÷ 200 × 100 = 11.24

  • Exhibit 1: Each 10 points of leasing moves the yield by 1.8 points; the 10 percent hurdle sits just below 80 percent.
  • Exhibit 2: The anchor costs about a point of yield and removes much of the leasing risk.

Recommendation

The campus is attractive if it can be leased quickly and the power arrives on time. It earns a yield on cost of about 12.2 percent and pays back in about 8.2 years on a building that lasts decades. First, 90 percent leasing at USD 150 per kW per month brings USD 32.4 million a year against USD 8 million of costs. Second, the return depends most on how fast the halls fill: every empty MW still costs its build money and its share of operating costs. The board's 10 percent hurdle is met once about 78 percent of the campus is leased. Third, the anchor tenant's discount to USD 130 costs about one point of yield, from 12.2 to 11.24 percent. That is a fair price for filling 8 MW before building. This is a capacity expansion, so the move is to phase it and pre-let it. The risk is that the grid connection or transformers arrive late, so the building sits empty. As a next step, sign an anchor tenant for the first phase before committing to build all 20 MW.

Risks

  • A late grid connection leaves capacity built but unleasable
  • A large tenant can push the rent down in exchange for signing early
  • Rupee and dollar exchange rates affect a cost base partly in rupees

Next steps

  • Sign the 8 MW anchor before construction starts on phase one
  • Get a written date and penalty terms for the 30 MW grid connection
  • Order transformers now, since they take about 12 months to arrive
Timed math drill

A new AI site in the UAE has a 100 MW grid connection. The design PUE is 1.25, so part of the power goes to cooling and losses. Each AI rack draws 125 kW. How many racks can the site power?

Worked case

Profit per GPU for a GPU cloud in Singapore

Case

A GPU cloud (a neocloud) in Singapore rents out AI GPUs by the hour and reports in USD. Each GPU costs USD 35,000 all in, including its share of the server and network, and is written off over five years. It sells GPU time at USD 2.50 an hour and expects the GPUs to be busy 70 percent of the 8,760 hours in a year. Each GPU draws 1.25 kW including cooling, at USD 0.10 per kWh, around the clock. Colocation rent and support cost USD 2,000 per GPU a year. What is yearly profit per GPU before interest and tax, and at what utilisation does it break even? (Figures are illustrative.)

The companies and figures in this case are made up for practice, unless a source is named.

Questions to ask

Situation

  • How big is the GPU cloud?

    What the interviewer says

    It runs about 4,000 GPUs in a rented hall in a Singapore data centre and sells GPU time by the hour.

History

  • How have GPU prices moved?

    What the interviewer says

    AWS cut its H100 on-demand prices by up to about 45 percent in June 2025. Specialist clouds such as Lambda listed H100s at about USD 4 an hour in September 2026.

Objective

  • What are investors asking?

    What the interviewer says

    Whether each GPU earns enough to justify buying 2,000 more.

Financials

  • What does a GPU cost, and how long is it written off over?

    What the interviewer says

    USD 35,000 all in, including its share of servers and network. It is written off over five years.

  • What does it sell for, and how busy are the GPUs?

    What the interviewer says

    USD 2.50 an hour on average, after discounts. GPUs are busy about 70 percent of the 8,760 hours in a year.

  • What are the running costs?

    What the interviewer says

    Each GPU draws 1.25 kW including cooling, at USD 0.10 per kWh. Rent and support cost USD 2,000 per GPU a year.

  • How were the GPUs paid for?

    What the interviewer says

    Loans cover 70 percent of the cost at 9 percent a year. The rest came from investors.

Customers

  • Who are the customers?

    What the interviewer says

    Mostly AI start-ups on monthly contracts. The largest customer buys about 25 percent of all hours.

Competitors

  • Who does it compete with?

    What the interviewer says

    Large cloud providers and other specialist GPU clouds in Asia, several of which offer discounts for one-year commitments.

Operations

  • How steady is utilisation?

    What the interviewer says

    It ranged from 55 to 80 percent by month over the last year.

  • Anything else in the plan?

    What the interviewer says

    The firm is trialling liquid cooling on one row of racks and moving its office to a new building.

Constraints

  • Is power a limit?

    What the interviewer says

    Yes. The hall has power for about 6,500 GPUs in total, and extra power in Singapore is hard to get.

Exhibits

Exhibit 1

Yearly profit per GPU before interest and tax (USD)

Waterfall chart: Yearly profit per GPU before interest and tax (USD). Values in USD. Revenue, total: 15,330; Depreciation, change: -7,000; Power, change: -1,095; Rent and support, change: -2,000; Profit, total: 5,235.

Illustrative figures.

Exhibit 2

Yearly profit per GPU under each change (USD)

Bar chart: Yearly profit per GPU under each change (USD). Values in USD. Base case: 5,235; Utilisation 50 percent: 855; Price USD 1.80: 942.6; Three-year chip life: 568.33.

Illustrative. One change at a time from the base case.

Solution

Show the solution

Structure

  • Profit per GPU = hours sold x price minus (depreciation + power + facility)
    • Hours sold = 8,760 x utilisation
    • Depreciation = GPU cost / useful life
    • Power = kW x 8,760 hours x price per kWh
    • Break-even utilisation = total costs / (8,760 x price)

Analysis

  1. 1. Hours sold

    70 percent of 8,760 hours.

    GPU hours sold a year: 8,760 × 0.7 = 6,132

  2. 2. Revenue

    6,132 hours at USD 2.50.

    Revenue per GPU a year (USD): 8,760 × 0.7 × 2.5 = 15,330

  3. 3. Depreciation

    USD 35,000 over five years.

    Depreciation per GPU a year (USD): 35,000 ÷ 5 = 7,000

  4. 4. Power

    1.25 kW for 8,760 hours at USD 0.10 per kWh (power is drawn even when idle, a simplification).

    Power cost per GPU a year (USD): 1.25 × 8,760 × 0.1 = 1,095

  5. 5. Profit per GPU

    Revenue minus depreciation, power and USD 2,000 of facility costs.

    Profit per GPU a year before interest and tax (USD): 15,330 - 7,000 - 1,095 - 2,000 = 5,235

  6. 6. Break-even utilisation

    Total costs of USD 10,095 divided by the revenue at full use, 8,760 hours at USD 2.50.

    Break-even utilisation (percent): (7,000 + 1,095 + 2,000) ÷ (8,760 × 2.5) × 100 = 46.1

  7. 7. Profit at a three-year chip life

    Depreciation rises to USD 35,000 over three years.

    Profit per GPU, three-year life (USD): 15,330 - 35,000 ÷ 3 - 1,095 - 2,000 = 568

  8. 8. Break-even price at 70 percent utilisation

    Yearly costs of USD 10,095 over 6,132 hours sold.

    Break-even price per GPU hour (USD): 10,095 ÷ (8,760 × 0.7) = 1.65

  9. 9. Interest on the GPU loan

    Loans cover 70 percent of the GPU cost at 9 percent a year, in the first year.

    Profit per GPU after first-year interest (USD): 5,235 - 35,000 × 0.7 × 0.09 = 3,030

  • Exhibit 1: Depreciation is the largest cost, so the assumed chip life matters as much as the price.
  • Exhibit 2: Any one of three plausible changes wipes out most of the profit.

Recommendation

The GPU cloud makes money at these numbers, about USD 5,235 per GPU a year. But it should lock in long contracts, because profit is very sensitive to price and chip life. First, it breaks even at about 46 percent utilisation, so a fall in demand hurts quickly. Second, if the price drops to USD 1.80 an hour at the same 70 percent utilisation, profit falls to under USD 1,000 per GPU. If the chips must be written off over three years instead of five, depreciation rises to about USD 11,700 and profit falls to under USD 600. The break-even price is only about USD 1.65 an hour. Third, after interest on the GPU loans, first-year profit is about USD 3,030 per GPU. This business is a bet on utilisation and price over the chip's life, so the move is to match contract length to that life. The risk is that newer chips make these GPUs cheaper to rent within two or three years. As a next step, compare the length of customer contracts with the life assumed for the chips.

Risks

  • Newer, faster chips push down the price customers will pay for older GPUs
  • Interest on the debt used to buy GPUs is not in this profit figure
  • A single large customer leaving would cut utilisation sharply

Next steps

  • Offer a discount for two- and three-year reserved contracts and measure take-up
  • Hold off buying 2,000 more GPUs until reserved contracts cover at least half the hours
  • Review the five-year chip life with the auditors against resale prices for older GPUs
Timed math drill

In the Singapore GPU case, the price falls from USD 2.50 to USD 1.80 an hour, utilisation stays at 70 percent of 8,760 hours, and yearly costs stay at USD 10,095 per GPU. What is the new yearly profit per GPU, in USD? Round to the nearest dollar.

The capex cycle

Data centres are built in waves. When demand is hot, everyone orders chips, transformers and cooling at once, prices and delivery times rise, and capacity arrives two or three years later, sometimes all at the same time. If demand then slows, rents and GPU prices fall and the newest capacity sits empty. When you judge a big investment, ask what happens if prices fall by a third just as the capacity comes online.

Check your understanding

Quick check

A GPU cloud writes its chips off over three years instead of five. What happens to its yearly profit per GPU, other things equal?

Firm processes and online tests change from year to year and differ by office. Confirm the current steps on the firm’s own careers page.

Next lesson: Data centres and AI compute: players, trends and cases

Sources