Data centre economics: per MW, per rack and per GPU hour
Work out rent and return per megawatt for colocation, racks from a power budget, and profit per GPU hour for an AI cloud, and see why utilisation, price and chip life decide everything.
Lesson 2 of 3 · 12 min
The idea
Two businesses sit in one building. Colocation earns rent per kW for 10 to 15 years on a building that lasts decades, so it looks like property. A GPU cloud earns per GPU hour on chips that lose value in a few years, so it lives or dies on utilisation (the share of hours its chips are rented out), price and how fast the chips must be paid back.
| Item | Range | Source |
|---|---|---|
| Build cost, all in, greenfield, US and Canada, excluding chips | About USD 8.9 million to 23.3 million per MW, up about 21 percent since late 2024 | Cushman & Wakefield 2026 cost guide, as reported |
| Colocation asking rent, Silicon Valley | About USD 180 to 275 per kW per month | CBRE, second half of 2025 |
| Primary US market vacancy | About 1.4 percent, a record low | CBRE, H1 2026 |
| H100 GPU, on-demand, specialist GPU cloud list price | About USD 4 per GPU hour | Lambda price list, September 2026 |
| H100 GPU, AWS on-demand price cut in June 2025 | Up to about 45 percent | AWS, June 2025 |
So-what
Prices differ a lot by market, contract length and size: a 20 MW hyperscale lease pays far less per kW than a few racks, and long GPU contracts cost less per hour than on-demand. Treat these as reference points, not a price list.
Worked case
Return per MW for a colocation campus near Mumbai
Case
A developer plans a 20 MW colocation campus near Mumbai and reports in USD. It costs USD 10 million per MW of IT load to build, excluding the customers' servers. It expects to lease 90 percent of the capacity at an average rent of USD 150 per kW per month; customers pay for their own electricity on top. Operating costs that are not passed through (staff, maintenance, insurance, security) are USD 400,000 per MW of built capacity a year. What are yearly revenue and operating profit, the yield on cost, and the simple payback? (Figures are illustrative.)
The companies and figures in this case are made up for practice, unless a source is named.
Questions to ask
Situation
Who is the developer, and what is the plan?
What the interviewer says
The data centre arm of a Mumbai property group. It plans 20 MW of IT load on one plot in Navi Mumbai, built in two 10 MW phases.
History
Has the group built data centres before?
What the interviewer says
No. It has built office parks for 15 years and bought this land in 2024.
Objective
What does the board need to decide?
What the interviewer says
Whether to approve USD 200 million. It wants a yield on cost of at least 10 percent before depreciation.
Financials
What does it cost to build and run?
What the interviewer says
USD 10 million per MW of IT load, excluding customers' servers. Running costs that are not passed through are USD 400,000 per MW a year.
What will customers pay?
What the interviewer says
About USD 150 per kW of IT load per month, plus their own electricity, which is passed through at cost.
Market
How tight is the market?
What the interviewer says
For reference, CBRE reported US primary market vacancy of about 1.4 percent in the first half of 2026. The group's broker puts Mumbai rents at USD 120 to 170 per kW per month.
Is USD 10 million per MW a normal build cost?
What the interviewer says
Cushman and Wakefield's 2026 guide put US and Canada costs at about USD 8.9 million to 23.3 million per MW, up about 21 percent since late 2024.
Customers
Who wants the space?
What the interviewer says
Two cloud firms and a bank are in talks. One cloud firm will take 8 MW at USD 130 per kW per month if it signs before construction.
Competitors
Who else is building nearby?
What the interviewer says
Three large operators are building campuses in Navi Mumbai, adding several hundred MW over the next three years.
Operations
When will power be available?
What the interviewer says
The state utility has promised a 30 MW connection in 18 months, enough for 20 MW of IT load plus cooling. Transformers take about 12 months to arrive.
What cooling is planned?
What the interviewer says
A design PUE of 1.4, with an option to add liquid cooling for AI racks later. A rooftop solar plan is also being studied.
Constraints
How will it be funded?
What the interviewer says
Lenders will fund 60 percent if the group puts in 40 percent as equity.
Exhibits
Exhibit 1
Bar chart: Yield on cost by share of the campus leased, at USD 150 per kW per month (percent). 70 percent leased: 8.6 percent; 80 percent leased: 10.4 percent; 90 percent leased: 12.2 percent; 100 percent leased: 14 percent.
Illustrative figures. Build cost USD 200 million; running costs USD 8 million a year.
Exhibit 2
| Case | Revenue | Operating profit | Yield on cost (percent) |
|---|---|---|---|
| 18 MW leased at USD 150 | 32.4 | 24.4 | 12.2 |
| 8 MW at USD 130, 10 MW at USD 150 | 30.48 | 22.48 | 11.24 |
Illustrative figures.
Solution
Show the solutionHide the solution
Structure
- Return per MW = (rent from leased MW minus operating costs) / build cost
- Revenue = MW x 1,000 kW x leased share x rent per kW x 12 months
- Operating profit = revenue minus operating costs
- Yield on cost = operating profit / build cost
- Payback = build cost / operating profit, in years
Analysis
1. Build cost
20 MW at USD 10 million each, in USD millions.
Build cost (USD millions): 20 × 10 = 200
2. Yearly rent
20,000 kW, 90 percent leased, at USD 150 a month for 12 months, in USD millions.
Yearly revenue (USD millions): 20 × 1,000 × 0.9 × 150 × 12 ÷ 1,000,000 = 32.4
3. Operating costs
USD 0.4 million per MW on all 20 MW built.
Yearly operating costs (USD millions): 20 × 0.4 = 8
4. Operating profit
Revenue minus operating costs, before depreciation, interest and tax.
Yearly operating profit before depreciation (USD millions): 32.4 - 8 = 24.4
5. Yield on cost
Operating profit divided by build cost.
Yield on cost (percent): 24.4 ÷ 200 × 100 = 12.2
6. Simple payback
Build cost divided by yearly operating profit.
Simple payback (years): 200 ÷ 24.4 = 8.2
7. Leased share needed for a 10 percent yield
The board wants USD 20 million of operating profit on USD 200 million, so revenue must cover that plus USD 8 million of costs. Full leasing would bring USD 36 million.
Leased share needed (fraction): (200 × 0.1 + 8) ÷ (20 × 1,000 × 150 × 12 ÷ 1,000,000) = 0.7778
8. Revenue with the anchor tenant
The anchor takes 8 MW at USD 130; another 10 MW lets at USD 150, so 90 percent is still leased.
Yearly revenue with the anchor (USD millions): (8,000 × 130 + 10,000 × 150) × 12 ÷ 1,000,000 = 30.48
9. Yield on cost with the anchor
Revenue minus USD 8 million of costs, over USD 200 million.
Yield on cost with the anchor (percent): (30.48 - 8) ÷ 200 × 100 = 11.24
- Exhibit 1: Each 10 points of leasing moves the yield by 1.8 points; the 10 percent hurdle sits just below 80 percent.
- Exhibit 2: The anchor costs about a point of yield and removes much of the leasing risk.
Recommendation
The campus is attractive if it can be leased quickly and the power arrives on time. It earns a yield on cost of about 12.2 percent and pays back in about 8.2 years on a building that lasts decades. First, 90 percent leasing at USD 150 per kW per month brings USD 32.4 million a year against USD 8 million of costs. Second, the return depends most on how fast the halls fill: every empty MW still costs its build money and its share of operating costs. The board's 10 percent hurdle is met once about 78 percent of the campus is leased. Third, the anchor tenant's discount to USD 130 costs about one point of yield, from 12.2 to 11.24 percent. That is a fair price for filling 8 MW before building. This is a capacity expansion, so the move is to phase it and pre-let it. The risk is that the grid connection or transformers arrive late, so the building sits empty. As a next step, sign an anchor tenant for the first phase before committing to build all 20 MW.
Risks
- A late grid connection leaves capacity built but unleasable
- A large tenant can push the rent down in exchange for signing early
- Rupee and dollar exchange rates affect a cost base partly in rupees
Next steps
- Sign the 8 MW anchor before construction starts on phase one
- Get a written date and penalty terms for the 30 MW grid connection
- Order transformers now, since they take about 12 months to arrive
A new AI site in the UAE has a 100 MW grid connection. The design PUE is 1.25, so part of the power goes to cooling and losses. Each AI rack draws 125 kW. How many racks can the site power?
Worked case
Profit per GPU for a GPU cloud in Singapore
Case
A GPU cloud (a neocloud) in Singapore rents out AI GPUs by the hour and reports in USD. Each GPU costs USD 35,000 all in, including its share of the server and network, and is written off over five years. It sells GPU time at USD 2.50 an hour and expects the GPUs to be busy 70 percent of the 8,760 hours in a year. Each GPU draws 1.25 kW including cooling, at USD 0.10 per kWh, around the clock. Colocation rent and support cost USD 2,000 per GPU a year. What is yearly profit per GPU before interest and tax, and at what utilisation does it break even? (Figures are illustrative.)
The companies and figures in this case are made up for practice, unless a source is named.
Questions to ask
Situation
How big is the GPU cloud?
What the interviewer says
It runs about 4,000 GPUs in a rented hall in a Singapore data centre and sells GPU time by the hour.
History
How have GPU prices moved?
What the interviewer says
AWS cut its H100 on-demand prices by up to about 45 percent in June 2025. Specialist clouds such as Lambda listed H100s at about USD 4 an hour in September 2026.
Objective
What are investors asking?
What the interviewer says
Whether each GPU earns enough to justify buying 2,000 more.
Financials
What does a GPU cost, and how long is it written off over?
What the interviewer says
USD 35,000 all in, including its share of servers and network. It is written off over five years.
What does it sell for, and how busy are the GPUs?
What the interviewer says
USD 2.50 an hour on average, after discounts. GPUs are busy about 70 percent of the 8,760 hours in a year.
What are the running costs?
What the interviewer says
Each GPU draws 1.25 kW including cooling, at USD 0.10 per kWh. Rent and support cost USD 2,000 per GPU a year.
How were the GPUs paid for?
What the interviewer says
Loans cover 70 percent of the cost at 9 percent a year. The rest came from investors.
Customers
Who are the customers?
What the interviewer says
Mostly AI start-ups on monthly contracts. The largest customer buys about 25 percent of all hours.
Competitors
Who does it compete with?
What the interviewer says
Large cloud providers and other specialist GPU clouds in Asia, several of which offer discounts for one-year commitments.
Operations
How steady is utilisation?
What the interviewer says
It ranged from 55 to 80 percent by month over the last year.
Anything else in the plan?
What the interviewer says
The firm is trialling liquid cooling on one row of racks and moving its office to a new building.
Constraints
Is power a limit?
What the interviewer says
Yes. The hall has power for about 6,500 GPUs in total, and extra power in Singapore is hard to get.
Exhibits
Exhibit 1
Waterfall chart: Yearly profit per GPU before interest and tax (USD). Values in USD. Revenue, total: 15,330; Depreciation, change: -7,000; Power, change: -1,095; Rent and support, change: -2,000; Profit, total: 5,235.
Illustrative figures.
Exhibit 2
Bar chart: Yearly profit per GPU under each change (USD). Values in USD. Base case: 5,235; Utilisation 50 percent: 855; Price USD 1.80: 942.6; Three-year chip life: 568.33.
Illustrative. One change at a time from the base case.
Solution
Show the solutionHide the solution
Structure
- Profit per GPU = hours sold x price minus (depreciation + power + facility)
- Hours sold = 8,760 x utilisation
- Depreciation = GPU cost / useful life
- Power = kW x 8,760 hours x price per kWh
- Break-even utilisation = total costs / (8,760 x price)
Analysis
1. Hours sold
70 percent of 8,760 hours.
GPU hours sold a year: 8,760 × 0.7 = 6,132
2. Revenue
6,132 hours at USD 2.50.
Revenue per GPU a year (USD): 8,760 × 0.7 × 2.5 = 15,330
3. Depreciation
USD 35,000 over five years.
Depreciation per GPU a year (USD): 35,000 ÷ 5 = 7,000
4. Power
1.25 kW for 8,760 hours at USD 0.10 per kWh (power is drawn even when idle, a simplification).
Power cost per GPU a year (USD): 1.25 × 8,760 × 0.1 = 1,095
5. Profit per GPU
Revenue minus depreciation, power and USD 2,000 of facility costs.
Profit per GPU a year before interest and tax (USD): 15,330 - 7,000 - 1,095 - 2,000 = 5,235
6. Break-even utilisation
Total costs of USD 10,095 divided by the revenue at full use, 8,760 hours at USD 2.50.
Break-even utilisation (percent): (7,000 + 1,095 + 2,000) ÷ (8,760 × 2.5) × 100 = 46.1
7. Profit at a three-year chip life
Depreciation rises to USD 35,000 over three years.
Profit per GPU, three-year life (USD): 15,330 - 35,000 ÷ 3 - 1,095 - 2,000 = 568
8. Break-even price at 70 percent utilisation
Yearly costs of USD 10,095 over 6,132 hours sold.
Break-even price per GPU hour (USD): 10,095 ÷ (8,760 × 0.7) = 1.65
9. Interest on the GPU loan
Loans cover 70 percent of the GPU cost at 9 percent a year, in the first year.
Profit per GPU after first-year interest (USD): 5,235 - 35,000 × 0.7 × 0.09 = 3,030
- Exhibit 1: Depreciation is the largest cost, so the assumed chip life matters as much as the price.
- Exhibit 2: Any one of three plausible changes wipes out most of the profit.
Recommendation
The GPU cloud makes money at these numbers, about USD 5,235 per GPU a year. But it should lock in long contracts, because profit is very sensitive to price and chip life. First, it breaks even at about 46 percent utilisation, so a fall in demand hurts quickly. Second, if the price drops to USD 1.80 an hour at the same 70 percent utilisation, profit falls to under USD 1,000 per GPU. If the chips must be written off over three years instead of five, depreciation rises to about USD 11,700 and profit falls to under USD 600. The break-even price is only about USD 1.65 an hour. Third, after interest on the GPU loans, first-year profit is about USD 3,030 per GPU. This business is a bet on utilisation and price over the chip's life, so the move is to match contract length to that life. The risk is that newer chips make these GPUs cheaper to rent within two or three years. As a next step, compare the length of customer contracts with the life assumed for the chips.
Risks
- Newer, faster chips push down the price customers will pay for older GPUs
- Interest on the debt used to buy GPUs is not in this profit figure
- A single large customer leaving would cut utilisation sharply
Next steps
- Offer a discount for two- and three-year reserved contracts and measure take-up
- Hold off buying 2,000 more GPUs until reserved contracts cover at least half the hours
- Review the five-year chip life with the auditors against resale prices for older GPUs
In the Singapore GPU case, the price falls from USD 2.50 to USD 1.80 an hour, utilisation stays at 70 percent of 8,760 hours, and yearly costs stay at USD 10,095 per GPU. What is the new yearly profit per GPU, in USD? Round to the nearest dollar.
The capex cycle
Data centres are built in waves. When demand is hot, everyone orders chips, transformers and cooling at once, prices and delivery times rise, and capacity arrives two or three years later, sometimes all at the same time. If demand then slows, rents and GPU prices fall and the newest capacity sits empty. When you judge a big investment, ask what happens if prices fall by a third just as the capacity comes online.
Check your understanding
Quick check
A GPU cloud writes its chips off over three years instead of five. What happens to its yearly profit per GPU, other things equal?
Firm processes and online tests change from year to year and differ by office. Confirm the current steps on the firm’s own careers page.
Next lesson: Data centres and AI compute: players, trends and cases
Sources
Math checked, facts checked against sources on 30 September 2026.
- CBRE: North America Data Center Trends H1 2026 (September 2026)
- CBRE press release: Silicon Valley data center market in the second half of 2025, asking rents USD 180 to 275 per kW per month (26 February 2026)
- IREI: Cushman & Wakefield releases 2026 Data Center Development Cost Guide, costs up 21 percent per MW since late 2024
- CRE Daily: data center construction costs jump 21 percent since 2024, USD 8.9 million to 23.3 million per MW (citing Cushman & Wakefield)
- AWS News Blog: up to 45 percent price reduction for Amazon EC2 NVIDIA GPU-accelerated instances (June 2025, official)
- Lambda: GPU cloud on-demand pricing page (official price list, checked September 2026)
- Supermicro: SuperServer SRS-GB200-NVL72 rack specification, power supplies rated at a total of 132 kW (official product page)
- Recognized public explanations of case-interview concepts and terms
Spotted something wrong or out of date? Report a mistake. We check every report and correct the page.