Return per MW for a colocation campus near Mumbai
Worked case with 12 questions and 2 exhibits
Case
A developer plans a 20 MW colocation campus near Mumbai and reports in USD. It costs USD 10 million per MW of IT load to build, excluding the customers' servers. It expects to lease 90 percent of the capacity at an average rent of USD 150 per kW per month; customers pay for their own electricity on top. Operating costs that are not passed through (staff, maintenance, insurance, security) are USD 400,000 per MW of built capacity a year. What are yearly revenue and operating profit, the yield on cost, and the simple payback? (Figures are illustrative.)
The companies and figures in this case are made up for practice, unless a source is named.
Questions to ask
Situation
Who is the developer, and what is the plan?
What the interviewer says
The data centre arm of a Mumbai property group. It plans 20 MW of IT load on one plot in Navi Mumbai, built in two 10 MW phases.
History
Has the group built data centres before?
What the interviewer says
No. It has built office parks for 15 years and bought this land in 2024.
Objective
What does the board need to decide?
What the interviewer says
Whether to approve USD 200 million. It wants a yield on cost of at least 10 percent before depreciation.
Financials
What does it cost to build and run?
What the interviewer says
USD 10 million per MW of IT load, excluding customers' servers. Running costs that are not passed through are USD 400,000 per MW a year.
What will customers pay?
What the interviewer says
About USD 150 per kW of IT load per month, plus their own electricity, which is passed through at cost.
Market
How tight is the market?
What the interviewer says
For reference, CBRE reported US primary market vacancy of about 1.4 percent in the first half of 2026. The group's broker puts Mumbai rents at USD 120 to 170 per kW per month.
Is USD 10 million per MW a normal build cost?
What the interviewer says
Cushman and Wakefield's 2026 guide put US and Canada costs at about USD 8.9 million to 23.3 million per MW, up about 21 percent since late 2024.
Customers
Who wants the space?
What the interviewer says
Two cloud firms and a bank are in talks. One cloud firm will take 8 MW at USD 130 per kW per month if it signs before construction.
Competitors
Who else is building nearby?
What the interviewer says
Three large operators are building campuses in Navi Mumbai, adding several hundred MW over the next three years.
Operations
When will power be available?
What the interviewer says
The state utility has promised a 30 MW connection in 18 months, enough for 20 MW of IT load plus cooling. Transformers take about 12 months to arrive.
What cooling is planned?
What the interviewer says
A design PUE of 1.4, with an option to add liquid cooling for AI racks later. A rooftop solar plan is also being studied.
Constraints
How will it be funded?
What the interviewer says
Lenders will fund 60 percent if the group puts in 40 percent as equity.
Exhibits
Exhibit 1
Bar chart: Yield on cost by share of the campus leased, at USD 150 per kW per month (percent). 70 percent leased: 8.6 percent; 80 percent leased: 10.4 percent; 90 percent leased: 12.2 percent; 100 percent leased: 14 percent.
Illustrative figures. Build cost USD 200 million; running costs USD 8 million a year.
Exhibit 2
| Case | Revenue | Operating profit | Yield on cost (percent) |
|---|---|---|---|
| 18 MW leased at USD 150 | 32.4 | 24.4 | 12.2 |
| 8 MW at USD 130, 10 MW at USD 150 | 30.48 | 22.48 | 11.24 |
Illustrative figures.
Solution
Show the solutionHide the solution
Structure
- Return per MW = (rent from leased MW minus operating costs) / build cost
- Revenue = MW x 1,000 kW x leased share x rent per kW x 12 months
- Operating profit = revenue minus operating costs
- Yield on cost = operating profit / build cost
- Payback = build cost / operating profit, in years
Analysis
1. Build cost
20 MW at USD 10 million each, in USD millions.
Build cost (USD millions): 20 × 10 = 200
2. Yearly rent
20,000 kW, 90 percent leased, at USD 150 a month for 12 months, in USD millions.
Yearly revenue (USD millions): 20 × 1,000 × 0.9 × 150 × 12 ÷ 1,000,000 = 32.4
3. Operating costs
USD 0.4 million per MW on all 20 MW built.
Yearly operating costs (USD millions): 20 × 0.4 = 8
4. Operating profit
Revenue minus operating costs, before depreciation, interest and tax.
Yearly operating profit before depreciation (USD millions): 32.4 - 8 = 24.4
5. Yield on cost
Operating profit divided by build cost.
Yield on cost (percent): 24.4 ÷ 200 × 100 = 12.2
6. Simple payback
Build cost divided by yearly operating profit.
Simple payback (years): 200 ÷ 24.4 = 8.2
7. Leased share needed for a 10 percent yield
The board wants USD 20 million of operating profit on USD 200 million, so revenue must cover that plus USD 8 million of costs. Full leasing would bring USD 36 million.
Leased share needed (fraction): (200 × 0.1 + 8) ÷ (20 × 1,000 × 150 × 12 ÷ 1,000,000) = 0.7778
8. Revenue with the anchor tenant
The anchor takes 8 MW at USD 130; another 10 MW lets at USD 150, so 90 percent is still leased.
Yearly revenue with the anchor (USD millions): (8,000 × 130 + 10,000 × 150) × 12 ÷ 1,000,000 = 30.48
9. Yield on cost with the anchor
Revenue minus USD 8 million of costs, over USD 200 million.
Yield on cost with the anchor (percent): (30.48 - 8) ÷ 200 × 100 = 11.24
- Exhibit 1: Each 10 points of leasing moves the yield by 1.8 points; the 10 percent hurdle sits just below 80 percent.
- Exhibit 2: The anchor costs about a point of yield and removes much of the leasing risk.
Recommendation
The campus is attractive if it can be leased quickly and the power arrives on time. It earns a yield on cost of about 12.2 percent and pays back in about 8.2 years on a building that lasts decades. First, 90 percent leasing at USD 150 per kW per month brings USD 32.4 million a year against USD 8 million of costs. Second, the return depends most on how fast the halls fill: every empty MW still costs its build money and its share of operating costs. The board's 10 percent hurdle is met once about 78 percent of the campus is leased. Third, the anchor tenant's discount to USD 130 costs about one point of yield, from 12.2 to 11.24 percent. That is a fair price for filling 8 MW before building. This is a capacity expansion, so the move is to phase it and pre-let it. The risk is that the grid connection or transformers arrive late, so the building sits empty. As a next step, sign an anchor tenant for the first phase before committing to build all 20 MW.
Risks
- A late grid connection leaves capacity built but unleasable
- A large tenant can push the rent down in exchange for signing early
- Rupee and dollar exchange rates affect a cost base partly in rupees
Next steps
- Sign the 8 MW anchor before construction starts on phase one
- Get a written date and penalty terms for the 30 MW grid connection
- Order transformers now, since they take about 12 months to arrive
Sources