Return per MW for a colocation campus near Mumbai

Worked case with 12 questions and 2 exhibits

Case

A developer plans a 20 MW colocation campus near Mumbai and reports in USD. It costs USD 10 million per MW of IT load to build, excluding the customers' servers. It expects to lease 90 percent of the capacity at an average rent of USD 150 per kW per month; customers pay for their own electricity on top. Operating costs that are not passed through (staff, maintenance, insurance, security) are USD 400,000 per MW of built capacity a year. What are yearly revenue and operating profit, the yield on cost, and the simple payback? (Figures are illustrative.)

The companies and figures in this case are made up for practice, unless a source is named.

Questions to ask

Situation

  • Who is the developer, and what is the plan?

    What the interviewer says

    The data centre arm of a Mumbai property group. It plans 20 MW of IT load on one plot in Navi Mumbai, built in two 10 MW phases.

History

  • Has the group built data centres before?

    What the interviewer says

    No. It has built office parks for 15 years and bought this land in 2024.

Objective

  • What does the board need to decide?

    What the interviewer says

    Whether to approve USD 200 million. It wants a yield on cost of at least 10 percent before depreciation.

Financials

  • What does it cost to build and run?

    What the interviewer says

    USD 10 million per MW of IT load, excluding customers' servers. Running costs that are not passed through are USD 400,000 per MW a year.

  • What will customers pay?

    What the interviewer says

    About USD 150 per kW of IT load per month, plus their own electricity, which is passed through at cost.

Market

  • How tight is the market?

    What the interviewer says

    For reference, CBRE reported US primary market vacancy of about 1.4 percent in the first half of 2026. The group's broker puts Mumbai rents at USD 120 to 170 per kW per month.

  • Is USD 10 million per MW a normal build cost?

    What the interviewer says

    Cushman and Wakefield's 2026 guide put US and Canada costs at about USD 8.9 million to 23.3 million per MW, up about 21 percent since late 2024.

Customers

  • Who wants the space?

    What the interviewer says

    Two cloud firms and a bank are in talks. One cloud firm will take 8 MW at USD 130 per kW per month if it signs before construction.

Competitors

  • Who else is building nearby?

    What the interviewer says

    Three large operators are building campuses in Navi Mumbai, adding several hundred MW over the next three years.

Operations

  • When will power be available?

    What the interviewer says

    The state utility has promised a 30 MW connection in 18 months, enough for 20 MW of IT load plus cooling. Transformers take about 12 months to arrive.

  • What cooling is planned?

    What the interviewer says

    A design PUE of 1.4, with an option to add liquid cooling for AI racks later. A rooftop solar plan is also being studied.

Constraints

  • How will it be funded?

    What the interviewer says

    Lenders will fund 60 percent if the group puts in 40 percent as equity.

Exhibits

Exhibit 1

Yield on cost by share of the campus leased, at USD 150 per kW per month (percent)(%)

Bar chart: Yield on cost by share of the campus leased, at USD 150 per kW per month (percent). 70 percent leased: 8.6 percent; 80 percent leased: 10.4 percent; 90 percent leased: 12.2 percent; 100 percent leased: 14 percent.

Illustrative figures. Build cost USD 200 million; running costs USD 8 million a year.

Exhibit 2

The campus with and without the anchor tenant (USD millions a year unless stated)
The campus with and without the anchor tenant (USD millions a year unless stated)
CaseRevenueOperating profitYield on cost (percent)
18 MW leased at USD 15032.424.412.2
8 MW at USD 130, 10 MW at USD 15030.4822.4811.24

Illustrative figures.

Solution

Show the solution

Structure

  • Return per MW = (rent from leased MW minus operating costs) / build cost
    • Revenue = MW x 1,000 kW x leased share x rent per kW x 12 months
    • Operating profit = revenue minus operating costs
    • Yield on cost = operating profit / build cost
    • Payback = build cost / operating profit, in years

Analysis

  1. 1. Build cost

    20 MW at USD 10 million each, in USD millions.

    Build cost (USD millions): 20 × 10 = 200

  2. 2. Yearly rent

    20,000 kW, 90 percent leased, at USD 150 a month for 12 months, in USD millions.

    Yearly revenue (USD millions): 20 × 1,000 × 0.9 × 150 × 12 ÷ 1,000,000 = 32.4

  3. 3. Operating costs

    USD 0.4 million per MW on all 20 MW built.

    Yearly operating costs (USD millions): 20 × 0.4 = 8

  4. 4. Operating profit

    Revenue minus operating costs, before depreciation, interest and tax.

    Yearly operating profit before depreciation (USD millions): 32.4 - 8 = 24.4

  5. 5. Yield on cost

    Operating profit divided by build cost.

    Yield on cost (percent): 24.4 ÷ 200 × 100 = 12.2

  6. 6. Simple payback

    Build cost divided by yearly operating profit.

    Simple payback (years): 200 ÷ 24.4 = 8.2

  7. 7. Leased share needed for a 10 percent yield

    The board wants USD 20 million of operating profit on USD 200 million, so revenue must cover that plus USD 8 million of costs. Full leasing would bring USD 36 million.

    Leased share needed (fraction): (200 × 0.1 + 8) ÷ (20 × 1,000 × 150 × 12 ÷ 1,000,000) = 0.7778

  8. 8. Revenue with the anchor tenant

    The anchor takes 8 MW at USD 130; another 10 MW lets at USD 150, so 90 percent is still leased.

    Yearly revenue with the anchor (USD millions): (8,000 × 130 + 10,000 × 150) × 12 ÷ 1,000,000 = 30.48

  9. 9. Yield on cost with the anchor

    Revenue minus USD 8 million of costs, over USD 200 million.

    Yield on cost with the anchor (percent): (30.48 - 8) ÷ 200 × 100 = 11.24

  • Exhibit 1: Each 10 points of leasing moves the yield by 1.8 points; the 10 percent hurdle sits just below 80 percent.
  • Exhibit 2: The anchor costs about a point of yield and removes much of the leasing risk.

Recommendation

The campus is attractive if it can be leased quickly and the power arrives on time. It earns a yield on cost of about 12.2 percent and pays back in about 8.2 years on a building that lasts decades. First, 90 percent leasing at USD 150 per kW per month brings USD 32.4 million a year against USD 8 million of costs. Second, the return depends most on how fast the halls fill: every empty MW still costs its build money and its share of operating costs. The board's 10 percent hurdle is met once about 78 percent of the campus is leased. Third, the anchor tenant's discount to USD 130 costs about one point of yield, from 12.2 to 11.24 percent. That is a fair price for filling 8 MW before building. This is a capacity expansion, so the move is to phase it and pre-let it. The risk is that the grid connection or transformers arrive late, so the building sits empty. As a next step, sign an anchor tenant for the first phase before committing to build all 20 MW.

Risks

  • A late grid connection leaves capacity built but unleasable
  • A large tenant can push the rent down in exchange for signing early
  • Rupee and dollar exchange rates affect a cost base partly in rupees

Next steps

  • Sign the 8 MW anchor before construction starts on phase one
  • Get a written date and penalty terms for the 30 MW grid connection
  • Order transformers now, since they take about 12 months to arrive