So What Club
Start free

Real estate and construction

Critical path

The longest chain of dependent tasks in a project, which sets how fast it can finish.

Last reviewed

What does Critical path mean?

The critical path is the longest sequence of tasks that depend on each other in a project. It sets the shortest possible time to finish: a delay to any task on it delays the whole project, while tasks off it have spare time, called float. The critical path method was developed in the late 1950s by James Kelley and Morgan Walker at Remington Rand and DuPont. Example: path A is foundations (3 months), then structure (6), then fit-out (4), 13 months in total; path B is ordering equipment (8), then installing it (3), 11 months. Path A is critical, so the project takes 13 months and path B has 2 months of float. To finish sooner, speed up tasks on path A.

Where does it come up in case interview prep?