A sorting machine for a Singapore warehouse
Worked case with 12 questions and 2 exhibits
Case
A Singapore logistics company can buy a warehouse sorting machine for SGD 240,000. It would cut costs by SGD 80,000 a year for six years, with no value at the end. The company's cost of capital is 10 percent a year, and the same budget could instead fund a software upgrade, shown in the table. The finance director asks whether the machine is worth buying.
Interviewer-led: the interviewer shows the two options and asks for payback, then NPV, then the IRR, and then which option to fund.
The companies and figures in this case are made up for practice, unless a source is named.
Questions to ask
Situation
What does the company do?
What the interviewer says
It runs a warehouse for online retailers, picking, packing and sorting about 15,000 parcels a day.
History
How is sorting done today?
What the interviewer says
By hand, with about 12 staff on each of two shifts.
Objective
What does the finance director want?
What the interviewer says
To fund whichever project adds the most value from this year's SGD 240,000 budget. Only one can be funded.
Financials
Are the savings after running costs such as maintenance and power?
What the interviewer says
Yes. The net figure is SGD 80,000 a year; the build-up is in the second exhibit.
Does the machine have any value at the end?
What the interviewer says
No.
What else could the money be used for?
What the interviewer says
A software upgrade with an expected return of about 15 percent a year.
Market
Is parcel volume stable?
What the interviewer says
It grew about 8 percent a year for three years. The two largest clients have contracts for four more years.
Customers
Do clients care how parcels are sorted?
What the interviewer says
They charge penalties for missorted parcels. The machine would cut those, and that saving is already inside the SGD 80,000.
Competitors
What do rival warehouses use?
What the interviewer says
The two largest local rivals installed similar machines in the last two years.
Operations
How sure are the savings?
What the interviewer says
The supplier's figure comes from three reference sites in the region.
Does the machine fit in the building?
What the interviewer says
Yes. It needs about 300 square meters, which became free when a client moved out.
Constraints
Are there limits on how we use the savings?
What the interviewer says
Staff would move to other roles, not be laid off. Installation takes about three months.
Exhibits
Exhibit 1
| Option | Upfront cost (SGD) | Yearly benefit | Life (years) |
|---|---|---|---|
| Sorting machine | 240,000 | SGD 80,000 of net savings a year, no value at the end | 6 |
| Software upgrade | 240,000 | About 15 percent return a year | Not stated |
Exhibit 2
Waterfall chart: Build-up of the machine's yearly saving (SGD thousands). Values in SGD thousands a year. Labor saved: four fewer staff a day, total: 120; Maintenance and power, change: -40; Net yearly saving, total: 80.
Source: illustrative supplier and company estimates.
Solution
Show the solutionHide the solution
Hypothesis
A three-year payback on a six-year machine looks healthy. My hypothesis is that it clears the 10 percent cost of capital comfortably, and that the real question is whether it beats the 15 percent software alternative.
Structure
- Payback, NPV, and IRR versus the alternativesThis comes from NPV = yearly savings discounted at the cost of capital minus the price of the machine, compared with the other use of the money.
- Payback
- Key: NPV at the 10 percent cost of capital
- IRR versus the 15 percent alternative
Analysis
1. Payback
SGD 240,000 against SGD 80,000 saved a year.
Payback (years): 240,000 ÷ 80,000 = 3
2. Savings before discounting
SGD 80,000 a year for six years, twice the cost. This is a 2 times cash multiple (a 100 percent net gain), but it ignores the time value of money.
Undiscounted savings (SGD): 80,000 × 6 = 480,000
3. Present value at 10 percent
Divide each year's saving by 1.1 once per year of waiting (1.21 is 1.1 x 1.1, and so on).
Present value of savings (SGD): 80,000 ÷ 1.1 + 80,000 ÷ 1.21 + 80,000 ÷ 1.331 + 80,000 ÷ 1.4641 + 80,000 ÷ 1.61051 + 80,000 ÷ 1.771561 = 348,421
4. NPV
Present value of savings minus the cost.
NPV at 10 percent (SGD): 348,420.86 - 240,000 = 108,421
5. Bracket the IRR: try 24 percent
At 24 percent the savings are still worth slightly more than the SGD 240,000 cost.
Present value at 24 percent (SGD): 80,000 ÷ 1.24 + 80,000 ÷ (1.24 × 1.24) + 80,000 ÷ (1.24 × 1.24 × 1.24) + 80,000 ÷ (1.24 × 1.24 × 1.24 × 1.24) + 80,000 ÷ (1.24 × 1.24 × 1.24 × 1.24 × 1.24) + 80,000 ÷ (1.24 × 1.24 × 1.24 × 1.24 × 1.24 × 1.24) = 241,638
6. Bracket the IRR: try 25 percent
At 25 percent they are worth slightly less than the cost, so the IRR is about 24 percent.
Present value at 25 percent (SGD): 80,000 ÷ 1.25 + 80,000 ÷ (1.25 × 1.25) + 80,000 ÷ (1.25 × 1.25 × 1.25) + 80,000 ÷ (1.25 × 1.25 × 1.25 × 1.25) + 80,000 ÷ (1.25 × 1.25 × 1.25 × 1.25 × 1.25) + 80,000 ÷ (1.25 × 1.25 × 1.25 × 1.25 × 1.25 × 1.25) = 236,114
- Exhibit 1: Both options use the same budget, so the machine must beat the software upgrade's 15 percent, not only the 10 percent cost of capital.
- Exhibit 2: The saving rests on labor; a third of it is eaten by running costs.
Recommendation
I recommend buying the machine. First, it pays back in three years. Its savings are worth about SGD 348,000 in today's money against a cost of SGD 240,000. That is an NPV of about SGD 108,000 at the 10 percent cost of capital. Second, its IRR is about 24 percent, above both the cost of capital and the 15 percent software alternative. Third, savings could fall by about 30 percent before the NPV reaches zero. The move in play is automation of a labor-heavy step. Warehousing runs on thin margins and parcel volumes keep growing, so replacing hand sorting with a machine locks in a lower cost per parcel as volume rises. Confirm the savings at a reference site before signing.
Risks
- Savings may be lower if volumes fall
- Maintenance costs may rise in later years
Next steps
- Visit a reference site using the same machine
- Negotiate a performance guarantee with the supplier
Strong and weak answers
A strong candidate
Computed payback, NPV, and a bracketed IRR, and compared the return with both the cost of capital and the alternative.
A weak candidate
Said yes because it "saves 80,000 a year" and "doubles the money," without discounting or comparing.
Sources
Spotted something wrong or out of date? Report a mistake. We check every report and correct the page.