So What Club

A national fund invests in a battery plant

Worked case with 10 questions and 1 exhibit

Case

A fictional national fund is asked to invest SAR 2 billion in a local electric vehicle battery plant. It expects to receive SAR 4 billion back after 8 years, and the plant should create 3,000 jobs. The fund requires a return of 8 percent a year, and its mandate also asks it to build local industry. The investment committee asks whether the return is enough, and what each job costs.

The companies and figures in this case are made up for practice, unless a source is named.

Questions to ask

Situation

  • Who else invests in the plant?

    What the interviewer says

    A foreign battery maker will own 60 percent and run the plant. The fund's SAR 2 billion buys the other 40 percent.

  • Where is the plant?

    What the interviewer says

    In an industrial city near a port, on land already owned by the government.

  • Has the partner's leadership been involved?

    What the interviewer says

    The partner's chief executive visited the site last month.

History

  • How have the fund's past industrial deals done?

    What the interviewer says

    Its earlier factory investments returned between 6 and 12 percent a year.

Objective

  • What is the fund's mandate?

    What the interviewer says

    To earn commercial returns and to help build new local industries, including jobs for citizens.

Financials

  • What does the whole plant cost?

    What the interviewer says

    About SAR 5 billion, shared in line with ownership.

Customers

  • Who will buy the batteries?

    What the interviewer says

    Half the output is pre-sold to a local electric vehicle maker, in which the fund also owns a stake.

Competitors

  • Will other plants compete?

    What the interviewer says

    Two other battery plants are planned in the wider region, both by large Asian makers.

Operations

  • How long until the plant produces?

    What the interviewer says

    Three years to build. First output in year four, full output in year five.

Constraints

  • Can the fund take a larger share?

    What the interviewer says

    No. The partner insists on majority control to run the plant.

Exhibit

Exhibit 1

Approximate yearly return under three scenarios (rule of 72, illustrative)(percent a year)

Bar chart: Approximate yearly return under three scenarios (rule of 72, illustrative). Values in percent a year. Plan: doubles in 8 years: 9; One-year delay: 8; Fund requirement: 8.

Solution

Show the solution

Structure

  • Financial return first, then strategic value
    • Multiple of money (MOIC)
    • Approximate yearly return with the rule of 72
    • Key: Investment per job created

Analysis

  1. 1. Multiple of money

    SAR 4 billion back on SAR 2 billion invested.

    Multiple on invested capital: 4 ÷ 2 = 2

  2. 2. Approximate yearly return

    By the rule of 72, money doubles in about 72 divided by the yearly return. It doubles in 8 years, so the return is about 72 divided by 8.

    Approximate yearly return (percent): 72 ÷ 8 = 9

  3. 3. Margin over the requirement

    9 percent against 8 percent.

    Return above requirement (points): 72 ÷ 8 - 8 = 1

  4. 4. Investment per job

    SAR 2 billion divided by 3,000 jobs.

    Investment per job created (SAR): 2,000,000,000 ÷ 3,000 = 666,667

  5. 5. A one-year delay

    Battery plants often start late. If the SAR 4 billion arrives after 9 years, the rule of 72 gives 72 divided by 9.

    Approximate yearly return with a one-year delay (percent): 72 ÷ 9 = 8

  6. 6. A 20 percent overrun

    If the fund must put in SAR 2.4 billion for the same SAR 4 billion back, the multiple falls below 2.

    Multiple on invested capital with a 20 percent overrun: 4 ÷ 2.4 = 1.67

  • The exhibit: One year of delay wipes out the whole cushion.

Recommendation

The fund can invest, but the deal only just clears its bar and needs protections, because doubling its money in 8 years gives about 9 percent a year against an 8 percent requirement. A 1 point cushion leaves little room: a one-year delay brings the return down to about 8 percent, and a 20 percent overrun cuts the multiple to about 1.67. The plant's 3,000 jobs cost about SAR 667,000 each, a trade-off the fund should state openly as part of its local industry mandate. The fund should ask the partner to carry overrun risk before committing.

Risks

  • Delay: new battery plants often take longer than planned to reach full output.
  • Cost overrun would fall partly on the fund unless the contract says otherwise.
  • Only half the output is pre-sold, so weak electric vehicle demand would hit returns.

Next steps

  • Test the return under delays and cost overruns before committing.
  • Negotiate a cap on the fund's share of any overrun, with the operating partner covering the rest.
  • Secure sales contracts for more of the plant's output.
Sources
Facts checked against sources on