OEE of a machining line in India

Worked case with 10 questions and 1 exhibit

Case

A fictional auto parts maker runs a machining line in Pune planned for 480 minutes a shift, and it stops for 48 minutes of breakdowns and changeovers. The ideal cycle time is 0.8 minutes per part. In a shift it makes 459 parts, of which 450 are good. A carmaker customer wants 20 percent more parts, and the plant head asks for the line's OEE and its biggest loss before buying a new line.

The companies and figures in this case are made up for practice, unless a source is named.

Questions to ask

Situation

  • What does the line make?

    What the interviewer says

    Steering knuckles for two carmakers. It runs three shifts a day, six days a week.

  • Has the plant won any recognition?

    What the interviewer says

    It won a state safety award last year. Its car park is being expanded.

History

  • Has OEE always been this level?

    What the interviewer says

    It was about 80 percent two years ago. Since then the line has gone from 4 to 9 part types.

Objective

  • What does the plant head need?

    What the interviewer says

    About 20 percent more good parts from next year, for one of its two carmaker customers.

Financials

  • What would a new line cost?

    What the interviewer says

    About INR 8 crore, with a lead time of nine months.

Customers

  • How strict is the customer?

    What the interviewer says

    It charges a penalty for late deliveries and audits quality twice a year.

Competitors

  • How do other plants compare?

    What the interviewer says

    The group's best plant runs similar lines at about 85 percent OEE.

Operations

  • What makes up the 48 minutes of stops?

    What the interviewer says

    One changeover of 30 minutes in a typical shift, and about 18 minutes of breakdowns.

  • Are short stops recorded?

    What the interviewer says

    No. Stops of one or two minutes are not logged by the operators.

Constraints

  • Can the line run more shifts?

    What the interviewer says

    No. The seventh day is kept for planned maintenance.

Exhibit

Exhibit 1

The three OEE factors on the Pune line (percent, illustrative)(percent)

Bar chart: The three OEE factors on the Pune line (percent, illustrative). Values in percent. Availability: 90; Performance: 85; Quality: 98; OEE: 75.

Solution

Show the solution

Structure

  • OEE = availability x performance x quality
    • Availability = run time divided by planned time
    • Performance = (parts made x ideal cycle time) divided by run time
    • Quality = good parts divided by parts made
    • Key: Extra output from fixing the losses, against a new line

Analysis

  1. 1. Availability

    Run time is 480 minus 48, which is 432 minutes.

    Availability (fraction): (480 - 48) ÷ 480 = 0.9

  2. 2. Performance

    459 parts at 0.8 minutes ideal is 367.2 minutes of ideal work in 432 minutes of running.

    Performance (fraction): 459 × 0.8 ÷ 432 = 0.85

  3. 3. Quality

    450 good out of 459.

    Quality (fraction): 450 ÷ 459 = 0.9804

  4. 4. OEE

    Multiply the three rates.

    OEE (fraction): 0.9 × 0.85 × (450 ÷ 459) = 0.75

  5. 5. Fix the speed loss

    In manufacturing, hidden capacity is cheaper than new capacity. Test 95 percent performance in the same 432 minutes of running.

    Parts per shift at 95 percent performance: 432 × 0.95 ÷ 0.8 = 513

  6. 6. Fix speed and changeovers

    Halving changeover time from 30 to 15 minutes cuts stops to 24 minutes in each shift with one changeover. Run time becomes 456 minutes at 95 percent performance and the same quality.

    Good parts per shift with both fixes: (480 - 24) × 0.95 ÷ 0.8 × (450 ÷ 459) = 531

  7. 7. Output gain

    Compare with 450 good parts today.

    Increase in good parts (percent): (530.88 ÷ 450 - 1) × 100 = 17.97

  • The exhibit: Speed is the biggest loss, then stops; quality is fine.

Recommendation

The plant should fix the line before buying a new one. OEE is 75 percent, and the biggest loss is performance (85 percent: the line runs slower than it should), then availability (90 percent). Quality is already high. Raising performance to 95 percent and halving changeover time would lift good parts from 450 to about 531 a shift, about 18 percent more. That covers almost all of the 20 percent the customer wants, for far less than the INR 8 crore a new line would cost.

Risks

  • A wrong ideal cycle time makes performance look better or worse than it is.
  • Small stops are not recorded today, so the speed loss may have causes that are slow to fix.
  • The last 2 percent of demand may still need overtime or a partner supplier.

Next steps

  • Record every stop over one minute for two weeks to find the causes of the speed loss.
  • Run a changeover reduction workshop on the most frequent part change.
  • Agree with the customer how the extra volume ramps up over six months.