A dairy plant in Gujarat that cannot keep up in summer
Worked case with 15 questions and 2 exhibits
Case
A dairy in Gujarat, India bottles flavoured milk and cannot keep up in summer. Shops want 5,500 bottles an hour, and the plant runs 16 hours a day. Each bottle earns INR 6 of contribution (price minus the costs that move with each bottle). The plant manager wants to buy a faster filling machine. What should the dairy do? (The dairy is fictional and the figures are illustrative.)
The companies and figures in this case are made up for practice, unless a source is named.
Questions to ask
Situation
What does the dairy make, and who buys it?
What the interviewer says
It bottles flavoured milk in 200 ml bottles, in four flavours. It sells to about 8,000 small shops and ice cream parlours across Gujarat.
Has anything changed in the product lately?
What the interviewer says
The dairy launched a new label design last year. Sales grew at about the same pace as in earlier years.
History
How long has the plant been short in summer?
What the interviewer says
Summer orders have grown about 15 percent a year for three years. Last summer was the first time shops could not get all they ordered.
Objective
What exactly does the plant manager want?
What the interviewer says
To meet summer orders of 5,500 bottles an hour. The manager has a quote for a faster filler that fills 12,000 bottles an hour, priced at INR 60 lakh.
Financials
What does each bottle earn?
What the interviewer says
Shops pay INR 20 a bottle. After milk, flavour, bottle, cap, label and crate, each bottle earns INR 6 of contribution.
What would other equipment cost?
What the interviewer says
A second labeller costs INR 25 lakh (2,500,000) installed. A fourth packing station, with a seasonal packer, costs about INR 1.5 lakh (150,000) for the summer.
Market
How long does the summer peak last?
What the interviewer says
Orders peak from March to June. Outside summer, shops want about 3,500 bottles an hour. The sales team has no firm count of days above 4,500.
Customers
What happens when a shop runs out?
What the interviewer says
The shop fills its fridge with another brand that day. Most shops come back to the dairy when stock returns.
Competitors
Who else sells flavoured milk here?
What the interviewer says
A large milk cooperative brand and two regional dairies. A dairy in Maharashtra launched a mango flavour this year, but it does not sell in Gujarat.
Operations
How many machines are at each step, and how fast are they?
What the interviewer says
Fill: 2 machines at 3,000 bottles an hour each. Cap: 1 at 7,000. Label: 1 at 4,500. Pack: 3 stations at 1,800 each.
How many hours does the line run?
What the interviewer says
Two shifts of 8 hours, so 16 hours a day through the summer. The night is used for cleaning.
How much time does each step lose to stops?
What the interviewer says
The stop log from last summer is in the second exhibit.
Where do the labels come from?
What the interviewer says
Printed rolls from a printer in Ahmedabad, on 15 days of credit. Supply has never run short.
Constraints
Is there space and money for new equipment?
What the interviewer says
There is floor space for one more labeller and one more packing station. The capital budget this year is INR 40 lakh.
How fast can new equipment arrive?
What the interviewer says
A second labeller takes about 6 weeks to deliver and install.
Exhibits
Exhibit 1
| Step | Machines or packing stations | Bottles per hour, each | Step capacity per hour |
|---|---|---|---|
| Fill | 2 | 3,000 | 6,000 |
| Cap | 1 | 7,000 | 7,000 |
| Label | 1 | 4,500 | 4,500 |
| Pack into crates | 3 | 1,800 | 5,400 |
Source: illustrative.
Exhibit 2
Bar chart: Hours lost to stops at each step last summer (hours). Values in hours. Fill: 20; Cap: 8; Label: 35; Pack into crates: 12.
Source: illustrative stop log.
Solution
Show the solutionHide the solution
Structure
- Output = the lower of demand and the slowest step; the value of a fix = extra bottles x contribution
- Capacity of each step = machines x rate
- Key: Output today and the shortfall against demand
- What the shortfall costs a day
- Options: fix the slowest step, then check the next one
Analysis
1. Filling capacity
Two fillers at 3,000 bottles an hour each.
Fill capacity (bottles per hour): 2 × 3,000 = 6,000
2. Packing capacity
Three packing stations at 1,800 bottles an hour each.
Pack capacity (bottles per hour): 3 × 1,800 = 5,400
3. Output today
Output is the lowest of demand and the four step capacities. Labelling is the bottleneck.
Output (bottles per hour): min(5,500; 6,000; 7,000; 4,500; 5,400) = 4,500
4. Shortfall
Shops want 5,500 an hour and the line makes 4,500.
Bottles short each hour: 5,500 - 4,500 = 1,000
5. What the shortfall costs
1,000 bottles an hour, for 16 hours, at INR 6 each.
Contribution lost a day (INR): 1,000 × 16 × 6 = 96,000
6. The faster filler
Even if filling doubled to 12,000 an hour, labelling still allows only 4,500. The filler adds nothing.
Output with a faster filler (bottles per hour): min(5,500; 12,000; 7,000; 4,500; 5,400) = 4,500
7. A second labeller
Labelling doubles to 9,000. Now packing, at 5,400, is the slowest step.
Output with two labellers (bottles per hour): min(5,500; 6,000; 7,000; 9,000; 5,400) = 5,400
8. The real gain
The gain is 900 bottles an hour, not 1,000, because packing becomes the limit.
Extra contribution a day (INR): (5,400 - 4,500) × 16 × 6 = 86,400
9. Payback
A second labeller costs INR 25 lakh (2,500,000). Divide by the daily gain.
Payback (summer days): 2,500,000 ÷ 86,400 = 28.94
10. Then fix packing cheaply
A fourth packing station takes packing to 7,200 an hour, so output reaches demand.
Output with four packing stations (bottles per hour): min(5,500; 6,000; 7,000; 9,000; 4 × 1,800) = 5,500
11. Payback of the fourth packing station
The station and a seasonal packer cost about INR 1.5 lakh (150,000) for the summer. It adds the last 100 bottles an hour.
Payback of the fourth station (summer days): 150,000 ÷ ((5,500 - 5,400) × 16 × 6) = 15.63
12. What an hour at the labeller is worth
Every hour the labeller stands still, the whole line loses 4,500 bottles. The other steps have spare capacity and can catch up; the labeller cannot.
Contribution lost per labeller hour (INR): 4,500 × 6 = 27,000
13. What last summer's labeller stops cost
The stop log shows 35 hours lost at the labeller last summer, each worth a full hour of line output.
Contribution lost to labeller stops (INR): 35 × 4,500 × 6 = 945,000
- Exhibit 1: Labelling, at 4,500 bottles an hour, is the slowest step, so the whole line makes 4,500 an hour however fast the fillers run.
- Exhibit 2: The labeller lost the most hours, and it is the one step where a lost hour cannot be made up later.
Recommendation
Do not buy the faster filler: labelling is the bottleneck, so a faster filler adds no output at all. Buy a second labeller instead. It lifts output from 4,500 to 5,400 bottles an hour and earns about INR 86,400 a day. So its INR 25 lakh cost pays back in about 29 summer days. Then add a fourth packing station for the peak season, which closes the last 100 bottles an hour of the gap. The risk is that summer demand is shorter or weaker than planned. Before buying, check how many days a year demand stays above 4,500 an hour. This is a small capacity investment aimed at one step, not a new line. Dairies earn a thin margin on each bottle, so output in the short peak carries much of the year's profit. That is why each lost hour at the labeller, worth INR 27,000, matters so much.
Risks
- Demand above 4,500 an hour may last only a few weeks
- A second labeller needs floor space and an operator on every shift
- If the new labeller arrives late in the season, part of the summer gain is lost
Next steps
- Count the days last summer when orders passed 4,500 bottles an hour
- Order the second labeller now, since delivery and installation take about 6 weeks
- Cut stops at the labeller first: plan roll changes and breaks so it never stands idle
- Hire a seasonal packer and set up the fourth packing station before the peak
Sources