The cost of a cubic metre of desalinated water, and why energy prices matter

Prints the prompt and every part you have revealed so far.

New to this industry?Start with its one-minute summary: Water, waste and utilities

The prompt

A developer is bidding for a 300,000 cubic metre a day reverse osmosis plant on the Red Sea coast of Saudi Arabia. It will cost USD 300 million to build, and the developer uses a capital recovery factor of 8 percent a year (the yearly payment that repays the plant and its financing). The plant runs 95 percent of the time. It uses 3.5 kWh of electricity per cubic metre at USD 0.04 per kWh. Other running costs are USD 0.08 per cubic metre. What is the cost per cubic metre? What if the electricity price doubles? (Figures are illustrative.)

Practice with a partner

1. Send the interviewer link to a friend. They read the case aloud and hold the answers.

2. You open the candidate view: you see only the prompt, a timer and a notes box.

3. Speak the case out loud. Your partner shares data when you ask, then scores you with the rubric.

Your turn first

Clarifying questions, with the interviewer's answers

My notes on this case

0 of 5,000 characters. Saves automatically.

Facts checked against sources on

Spotted something wrong or out of date? Report a mistake. We check every report and correct the page.