Case

A developer is bidding for a 300,000 cubic metre a day reverse osmosis plant on the Red Sea coast of Saudi Arabia. It will cost USD 300 million to build, and the developer uses a capital recovery factor of 8 percent a year (the yearly payment that repays the plant and its financing). The plant runs 95 percent of the time. It uses 3.5 kWh of electricity per cubic metre at USD 0.04 per kWh. Other running costs are USD 0.08 per cubic metre. What is the cost per cubic metre? What if the electricity price doubles? (Figures are illustrative.)

The companies and figures in this case are made up for practice, unless a source is named.

Questions to ask

Situation

  • What is being tendered?

    What the interviewer says

    A 300,000 cubic metre a day reverse osmosis plant on the Red Sea coast. The winner builds and runs it and sells the water to a state buyer for 25 years.

History

  • What have recent tenders been won at?

    What the interviewer says

    About USD 0.41 per cubic metre for Jubail 3A in 2020 and about USD 0.46 for Rabigh 4 in 2023, according to the developer and trade press.

Objective

  • What does the developer want?

    What the interviewer says

    To win with a tariff that still covers all costs and its financing.

Financials

  • What does the plant cost to build and finance?

    What the interviewer says

    USD 300 million. The developer uses a capital recovery factor of 8 percent a year.

  • What does it cost to run?

    What the interviewer says

    3.5 kWh of electricity per cubic metre at USD 0.04 per kWh from the grid, plus USD 0.08 per cubic metre for membranes, chemicals and staff.

Market

  • Why reverse osmosis rather than thermal?

    What the interviewer says

    It needs far less energy than older thermal plants that boil seawater, which is why the Gulf has moved to it.

Customers

  • How is the developer paid?

    What the interviewer says

    Per cubic metre delivered, at a tariff fixed for 25 years with only a small yearly inflation step.

Competitors

  • Who else is bidding?

    What the interviewer says

    Four consortia have prequalified. Two include power companies that own large solar plants.

Operations

  • How often will the plant run?

    What the interviewer says

    The design assumes 95 percent availability, after maintenance and cleaning.

  • Could the plant get cheaper power?

    What the interviewer says

    A solar and battery supplier offers power at about USD 0.035 per kWh, fixed for 25 years.

Constraints

  • Is there anything else the bid must cover?

    What the interviewer says

    The brine must be returned to the sea under environmental limits. The developer also moved its head office to Riyadh this year.

Exhibits

Exhibit 1

Cost of a cubic metre of desalinated water (USD)(USD per cubic metre)

Waterfall chart: Cost of a cubic metre of desalinated water (USD). Values in USD per cubic metre. Capital charge, total: 0.23; Energy, change: +0.14; Other running costs, change: +0.08; Total cost, total: 0.45.

Illustrative figures.

Exhibit 2

Total cost per cubic metre at different power prices (USD)(USD per cubic metre)

Bar chart: Total cost per cubic metre at different power prices (USD). Values in USD per cubic metre. USD 0.035 per kWh, locked: 0.43; USD 0.04 per kWh, grid today: 0.45; USD 0.06 per kWh: 0.52; USD 0.08 per kWh, doubled: 0.59.

Illustrative. Recent winning tariffs were about USD 0.41 and USD 0.46.

Solution

Show the solution

Structure

  • Cost per cubic metre = capital charge + energy + other running costs
    • Yearly output = daily capacity x 365 x availability
    • Capital charge = capex x capital recovery factor, divided by yearly output
    • Energy = kWh per cubic metre x price per kWh

Analysis

  1. 1. Yearly output

    300,000 cubic metres a day, 365 days, 95 percent of the time.

    Yearly output (cubic metres): 300,000 × 365 × 0.95 = 104,025,000

  2. 2. Capital charge per cubic metre

    USD 24 million a year (8 percent of 300 million) spread over the yearly output.

    Capital charge (USD per cubic metre): 300,000,000 × 0.08 ÷ 104,025,000 = 0.2307

  3. 3. Energy per cubic metre

    3.5 kWh at USD 0.04.

    Energy cost (USD per cubic metre): 3.5 × 0.04 = 0.14

  4. 4. Total cost

    Capital, energy and other running costs added.

    Total cost (USD per cubic metre): 300,000,000 × 0.08 ÷ 104,025,000 + 3.5 × 0.04 + 0.08 = 0.4507

  5. 5. Total cost if electricity doubles

    Energy becomes 3.5 kWh at USD 0.08, which is USD 0.28.

    Total cost with dearer power (USD per cubic metre): 300,000,000 × 0.08 ÷ 104,025,000 + 3.5 × 0.08 + 0.08 = 0.5907

  6. 6. Energy as a share of cost

    USD 0.14 of about USD 0.45.

    Energy share of cost (fraction): 0.14 ÷ (300,000,000 × 0.08 ÷ 104,025,000 + 0.14 + 0.08) = 0.3106

  7. 7. Yearly margin at a USD 0.46 bid

    The last winning tariff in the region, less the cost per cubic metre, times yearly output.

    Yearly margin at USD 0.46 (USD): 0.46 × 104,025,000 - 300,000,000 × 0.08 - (0.14 + 0.08) × 104,025,000 = 966,000

  8. 8. Cost with a locked solar and battery supply

    Power fixed at USD 0.035 per kWh for 25 years.

    Total cost with locked power (USD per cubic metre): 300,000,000 × 0.08 ÷ 104,025,000 + 3.5 × 0.035 + 0.08 = 0.4332

  • Exhibit 1: Half the cost is fixed capital; energy is the largest cost that can still move.
  • Exhibit 2: Above about USD 0.043 per kWh, the plant costs more than the last winning tariff.

Recommendation

The developer can bid near USD 0.45 per cubic metre only if it locks in cheap power. Energy is about a third of the cost, and doubling its price lifts the total to about USD 0.59, a rise of about 31 percent. First, the capital charge of about USD 0.23 is fixed once the plant is financed. Second, energy is the block most exposed to change, so a long power contract or its own solar supply matters. Third, at the last winning tariff of about USD 0.46, the plant would earn under USD 1 million a year above its costs. There is almost no room for error. Locking power at USD 0.035 brings the cost down to about USD 0.43 and makes a competitive bid safe. This is a backward integration move: securing the main input for the life of the contract. The risk is a tariff set too low to cover membranes and repairs. As a next step, price a solar power purchase agreement for the plant.

Risks

  • Plant downtime lowers yearly output and raises the capital charge per cubic metre
  • The brine left over must be handled so it does not harm the sea
  • Solar power covers daytime only, so the battery and grid mix must be priced with care

Next steps

  • Get firm quotes for a 25-year solar and battery power supply
  • Test the bid at 90 percent availability as well as 95
  • Check how close rival consortia are to cheap power of their own
Sources