Levelized cost of a solar plant, and why financing matters
Worked case with 10 questions and 1 exhibit
Case
Solmira Power (a fictional company) plans a 100 MW solar plant in a sunny region, with capex of USD 60 million and a 25 percent capacity factor. Yearly operation and maintenance costs USD 1.2 million. It wants to bid in a government auction for a 20-year power contract. The board asks for the levelized cost per MWh with a capital recovery factor of 8 percent a year, and with 11 percent, as investors may demand there.
The companies and figures in this case are made up for practice, unless a source is named.
Questions to ask
Situation
What experience does Solmira have?
What the interviewer says
It runs three solar plants in other countries. This would be its first in this country.
Who owns the land?
What the interviewer says
It is leased from a farming cooperative that grows dates nearby.
History
Has Solmira bid here before?
What the interviewer says
No. It watched the last auction and has been measuring sun on the site for two years.
Objective
What exactly is Solmira bidding for?
What the interviewer says
A 20-year contract to sell all the plant's power at a fixed price per MWh. The lowest price wins.
Financials
Where does the 8 percent come from?
What the interviewer says
A development bank offers a loan with a guarantee against late payment by the utility. That brings the capital recovery factor to 8 percent; without it, 11 percent.
Market
What did the last auction clear at?
What the interviewer says
USD 32 per MWh, a year ago. Four developers bid.
Customers
Who buys the power?
What the interviewer says
The state utility. Its credit rating is below investment grade, and it has paid some suppliers late in the past.
Competitors
Who will bid against Solmira?
What the interviewer says
Probably the same four developers. Two of them have cheap finance from their home countries.
Operations
How sure is the 25 percent capacity factor?
What the interviewer says
It comes from two years of sun measurements on the site. Similar plants nearby achieve 22 to 26 percent.
Constraints
Can the grid take all the power?
What the interviewer says
The connection is limited to 100 MW. The grid operator has cut output at other plants on very sunny days.
Exhibit
Exhibit 1
Bar chart: Levelized cost against the last auction price (USD per MWh, illustrative). Values in USD per MWh. LCOE, 8 percent financing: 27.4; LCOE, 8 percent, 22 percent capacity factor: 31.13; Last auction price: 32; LCOE, 11 percent financing: 35.62.
Solution
Show the solutionHide the solution
Structure
- LCOE = (yearly capital charge + yearly running cost) divided by yearly MWh
- Yearly MWh = MW x 8,760 hours x capacity factor
- Yearly capital charge = capex x capital recovery factor
- Running cost = operation and maintenance (no fuel for solar)
Analysis
1. Yearly output
100 MW for 8,760 hours at 25 percent.
Yearly output (MWh): 100 × 8,760 × 0.25 = 219,000
2. Yearly cost at 8 percent
Capital charge of 8 percent of 60, plus 1.2 of running costs.
Yearly cost (USD million): 60 × 0.08 + 1.2 = 6
3. LCOE at 8 percent
USD 6 million divided by 219,000 MWh.
LCOE (USD per MWh): 6 × 1,000,000 ÷ 219,000 = 27.4
4. LCOE at 11 percent
Capital charge of 11 percent of 60 is 6.6, plus 1.2, is 7.8 million a year.
LCOE at higher cost of capital (USD per MWh): (60 × 0.11 + 1.2) × 1,000,000 ÷ 219,000 = 35.62
5. Against the last auction price
Solar has no fuel, so it is a financing business: price is set by the cost of capital. The last auction cleared at USD 32 per MWh. At 8 percent, compare revenue at USD 32 on 219,000 MWh with the USD 6 million cost.
Yearly margin at USD 32 with 8 percent financing (USD million): (32 × 219,000 - 6,000,000) ÷ 1,000,000 = 1.01
6. If the sun disappoints
Test a 22 percent capacity factor at 8 percent financing: output falls to 192,720 MWh.
LCOE at a 22 percent capacity factor (USD per MWh): 6 × 1,000,000 ÷ (100 × 8,760 × 0.22) = 31.13
- The exhibit: Only cheap financing keeps the plant below the auction price.
Recommendation
Solmira should secure low-cost financing before it bids. The plant costs about USD 27.4 per MWh with an 8 percent capital recovery factor, but about USD 35.6 at 11 percent. That is 30 percent more for the same panels and sun, since capital is USD 4.8 million of the USD 6 million yearly cost. At the last auction price of USD 32, the plant earns about USD 1 million a year with cheap finance and loses money without it. So the guaranteed development bank loan matters more than cheaper panels.
Risks
- A lower capacity factor than planned raises LCOE: at 22 percent it is about USD 31.1, close to the auction price.
- LCOE ignores when the power is produced: solar power at noon may be worth less than power in the evening peak.
- The buyer is a state utility with a weak credit rating, so late payment is a real risk.
- Grid limits may force the plant to cut output on sunny days.
Next steps
- Agree the development bank guarantee before the auction deadline.
- Bid no lower than about USD 30 per MWh to keep a cushion for a weaker capacity factor.
- Ask the grid operator how often output cuts are expected.