Two projects, two different winners
Worked case with 11 questions and 2 exhibits
Case
A fictional manufacturer of steel structures and rail wagons in Poland can do only one of two projects this year (EUR millions). Project A, an automated welding line, costs 100 today and returns 60 in year 1 and 72 in year 2. Project B, an order to build rail wagons paid on delivery, costs 1,000 today and returns 1,150 in year 1. Its cost of capital is 10 percent. The board asks which project to choose.
The companies and figures in this case are made up for practice, unless a source is named.
Questions to ask
Situation
What does the company make?
What the interviewer says
Steel structures and rail wagons, from two plants in southern Poland. Revenue is about EUR 2,000 million a year.
Is anything else changing at the company?
What the interviewer says
It is moving its head office to Kraków next spring.
History
Has it built wagons for this customer before?
What the interviewer says
Three times, each about a third of the size of B. All were delivered on time.
Objective
What does the board care about most?
What the interviewer says
Adding value for the owners. The finance director also likes projects that pay back within two years.
Financials
How would each project be funded?
What the interviewer says
The company has EUR 300 million of cash and an unused credit line of 900 million at 6 percent.
How certain are the cash flows?
What the interviewer says
Here they are by year. A's savings come from labour and scrap, and the plant team rates them as likely. B's price is fixed in the contract. Steel for B is not yet bought and makes up about 40 percent of its cost.
Market
How is demand for wagons?
What the interviewer says
European rail operators are renewing old fleets. Steel prices have moved up to 20 percent within a year recently (illustrative).
Customers
Who is B's customer, and how does it pay?
What the interviewer says
A state-owned rail operator. It pays the full 1,150 on delivery in 12 months. Late delivery costs 1 percent of the price per week.
Competitors
Who else bid for the wagon order?
What the interviewer says
Two other wagon makers, one in Germany and one in Romania.
Operations
Can the plants handle each project?
What the interviewer says
B would fill one plant for the year. A takes four months to install and needs no extra staff.
Constraints
Why can it do only one?
What the interviewer says
Its engineering staff can manage only one large project at a time this year.
Exhibits
Exhibit 1
| Project | Today | Year 1 | Year 2 |
|---|---|---|---|
| A: automated welding line | -100 | 60 | 72 |
| B: rail wagon order | -1,000 | 1,150 | 0 |
Source: illustrative.
Exhibit 2
| Discount rate (percent) | NPV of A | NPV of B |
|---|---|---|
| 10 | 14.05 | 45.45 |
| 15 | 6.62 | 0 |
| 20 | 0 | -41.67 |
Source: illustrative, calculated from the cash flows.
Solution
Show the solutionHide the solution
Structure
- Choose the project that adds the most value today (this comes from the question: only one can be done)
- NPV of each at 10 percent
- IRR of each
- Payback of A, as a check on risk
Analysis
1. NPV of A
60 divided by 1.1, plus 72 divided by 1.21, minus 100.
NPV of A (EUR millions): 60 ÷ 1.1 + 72 ÷ 1.21 - 100 = 14.05
2. IRR of A
At 20 percent, 60 divided by 1.2 is 50 and 72 divided by 1.44 is 50, so the NPV is zero. The IRR is 20 percent.
NPV of A at 20 percent (EUR millions): 60 ÷ 1.2 + 72 ÷ 1.44 - 100 = 0
3. Payback of A
60 comes back in year 1. The other 40 takes 40 out of 72 of year 2.
Payback of A (years): 1 + (100 - 60) ÷ 72 = 1.56
4. NPV of B
1,150 divided by 1.1, minus 1,000.
NPV of B (EUR millions): 1,150 ÷ 1.1 - 1,000 = 45.45
5. IRR of B
A one-year project: the gain divided by the cost.
IRR of B (percent): (1,150 - 1,000) ÷ 1,000 × 100 = 15
6. Can it be funded?
Cash of 300 plus the unused credit line of 900, against B's cost of 1,000.
Funding left after B (EUR millions): 300 + 900 - 1,000 = 200
7. If steel costs 10 percent more
Steel for B is not yet bought and is about 400 of its 1,000 cost. A 10 percent rise adds 40 today.
NPV of B with steel 10 percent dearer (EUR millions): 1,150 ÷ 1.1 - (1,000 + 400 × 0.1) = 5.45
8. How late B can be
Late delivery costs 1 percent of the 1,150 price per week, paid in year 1. Weeks of delay that wipe out B's lead over A:
Weeks of delay that erase B's lead (weeks): (1,150 ÷ 1.1 - 1,000 - (60 ÷ 1.1 + 72 ÷ 1.21 - 100)) ÷ (1,150 × 0.01 ÷ 1.1) = 3
- Exhibit 1: B is ten times larger but over in one year. Project A is small and spread over two.
- Exhibit 2: B wins at the 10 percent cost of capital. Project A only wins at rates above about 14 percent, which is why IRR favours it.
Recommendation
The company should choose project B. It adds about EUR 45 million of value today against about EUR 14 million for A. IRR points the other way: 20 percent for A against 15 percent for B. That is because IRR ignores size. A high return on a small sum can add less value than a lower return on a large one. The choice is between an automation investment and a large contract that fills a plant for a year. Wagon building is order-driven and steel-heavy, so the margin on B rests on steel prices and on time. A 10 percent rise in steel would cut B's NPV to about 5 million, below A. About three weeks of late delivery would erase B's lead. The risk with B is that it puts EUR 1,000 million at stake for one year. As a next step, confirm the company can fund B. Also confirm that the 1,150 is as certain as A's cash flows.
Risks
- Steel is about 40 percent of B's cost and is not yet bought
- Penalties of about EUR 11.5 million a week for late delivery
- B uses most of the company's cash and credit line, leaving 200 million of headroom
Next steps
- Fix the steel price for B with suppliers before signing, or add a steel price clause to the contract
- Plan the build with a buffer of at least three weeks before the delivery date
- Keep project A for next year, when engineering staff are free